LMSEO (Labor, Materials, Sub, Equipment, Other)
In Ediphi, the LMSEO columns (Labor, Materials, Subcontractor, Equipment, and Other) make it easy for users to view the total cost breakdown of each line item, helping them better manage and support their budgets. This feature not only shows how each total is calculated, but also allows users to adjust the values to update the unit cost accordingly. The LMSEO columns are available in both the Detailed Summary and Line Items tabs.
Note: With Labor and Crews, some labor columns have different names:
- Labor Rate → Crew Rate
- Labor Hours → Crew Hours
- Hrs/UoM → Crew Hrs/UoM
- UoM/Hrs → UoM/Crew Hrs
This is just a cosmetic change to make things simpler. Note that a line item’s Crew Rate comes from an assigned labor crew.
The same applies in UPC Products. See Labor and Crews (Estimates) and Labor and Crews (UPC).
To start, click the arrow above Unit Cost to expand the LMSEO columns.

In this article
LMSEO Columns
Below is a breakdown of how each value is defined and calculated within the LMSEO columns:
Labor UC: Crew Rate x Crew Hrs/UoM = Labor UC.
- Changing the Crew Rate or Crew Hrs/UoM updates the Labor UC. If the line item has a labor crew, changing the Crew Rate overrides the crew’s rate.
- Entering a Labor UC sets the Crew Hrs/UoM to 1.
Crew Rate: (formerly Labor Rate): Labor cost per hour.
- When a labor crew is assigned, this value comes from the crew.
Crew Hrs/UoM: (formerly Hrs/UoM): Total crew hours needed per unit of measure.
Material UC: Cost of materials per unit.
Equip. UC: Cost of equipment per unit.
Sub UC: Cost of sub per unit.
Other UC: Other cost per unit.

Note: The Labor Crew, Individual Rate, Crew Hours, Individual Hours, Individual Hrs/UoM, and UoM/Individual Hrs columns are hidden by default. To show or hide them, click the ⋮ (more options) menu at the top right of the grid and check or uncheck Show Labor Columns.

LMSEO Totals Columns
Here's a breakdown of how the totals in the LMSEO columns are derived:
Total Labor: Labor UC x Qty
Total Material: Material UC x Qty
Total Sub: Sub UC x Qty
Total Equip: Equip. UC x Qty
Total Other: Other UC x Qty
Crew Hours: (formerly Labor Hours): Crew Hrs/UoM x Qty
UoM/Crew Hrs: (formerly UoM/hr): Shows unit of measurement per crew hour (ex. number of square feet painted in an hour)

Understanding the LMSEO Logic
The Line Item Total will always equal to the sum of its LMSEO components. To ensure this consistency, we've updated the platform: the override logic for LMSEO columns in Estimates has been removed. Here’s how it works:
- When updating line item totals, the following will occur:
- Partial UC Values: In the case where only some UC columns contain values, the allocation will be distributed across those columns only. Columns with no values will remain unchanged.
- Example: If 70% is in Labor and 30% in Materials, the auto-allocation will respect those percentages.
- No UC Values: If no values exist in any columns, Ediphi will place the entire entered amount into the Sub column, only if no rates exist (it will not spread across other columns).
- Crew Rate & Crew Hrs/UoM Behavior: If a line item has values in both Crew Rate and Crew Hrs/UoM:
- Updating the Total will recalculate Crew Hrs/UoM.
- The Crew Rate will remain unchanged.
- Example: Crew Rate: 80 x Crew Hrs/UoM: 12 → Total = 960. If the Total is overridden to 1,200, Crew Hrs/UoM updates to 15, and Crew Rate stays at 80.
- Clearing a Total: When a Total is cleared by a user, all LMSEO values for that line item will reset to null (-), except Crew Rate and Crew Hrs/UoM, which will remain.
- Labor UC Value Entry: Entering a Labor UC value automatically sets:
- Crew Hrs/UoM = 1
- Crew Rate = Entered value (only when no Crew Rate exists)
- Example: If $1,000 is entered, the Crew Hrs/UoM will equal 1, and the Crew Rate will equal $1,000.
- Partial UC Values: In the case where only some UC columns contain values, the allocation will be distributed across those columns only. Columns with no values will remain unchanged.
Note: Existing estimates are not impacted until a line item within is edited and triggers a re-calculation of the whole estimate.
Note: If a line item has a labor crew assigned, entering a new value in Crew Rate overrides the crew’s rate, and the line item keeps that rate even if the crew changes. Entering a labor rate through Bulk Edit, Update All Similar, or the Edit Line Item window also overrides the Crew Rate. To go back to the crew’s rate, clear the Crew Rate cell.
LMSEO and Assemblies
Assemblies are unique in that they have their own logic which determines parent line items. Here’s how it works:
- The Total of a parent line item equals the sum of all Assembly line item totals
- (Parent line item Total = sum of it’s Assembly line item totals).
- The Crew Rate of a parent line item equals the Labor UC divided by Crew Hrs/UoM (back-calculated)
- (Crew Rate = Labor UC / Crew Hrs/UoM)
- The Quantity of a parent line item equals the quantity of the selected Assembly Quantity line item
- (Parent line item Quantity = selected Assembly Quantity line item’s Quantity).
- The Unit Cost of a parent line item equals the Total divided by Quantity of the parent line item
- (Unit Cost = Parent line item Total/Parent line item Quantity).
- The Crew Hrs/UoM of a parent line item is inherited from the selected child
- (Crew Hrs/UoM = selected Assembly Quantity line item’s Crew Hrs/UoM)
- The Labor UC, Material UC, Equip. UC, Sub UC, and Other UC of a parent line item are distributed proportionally based on children’s LMSEO ratios
- (sum of Assembly line item Material UC/sum of Assembly line item Unit Costs = percentage carried into parent Material UC)
Note: Labor crews can be assigned to child line items in an assembly, but not to the assembly parent. If you convert a line item that has a crew into an assembly, the crew is removed.
If you have any questions, feel free to contact our support team and we'll be happy to help!