Using the Labor Gantt tab (GCs & GRs)

Within Ediphi, you have the ability to manage staffing and organize your schedule activities via the Labor Gantt tab in the General Conditions & General Requirements (GCs & GRs) module.

In this article

Labor Gantt Overview

The Labor Gantt tab is great for organizing and managing your activities (Schedule or GR Labor) throughout the project lifecycle . You have the ability to adjust a staff's work schedule in this view as well as the Staffing tab. This view will show all added phases from the Staffing tab. Keep in mind, you will need to add staff in the Staffing tab before you see the phases and staff in the Labor Gantt.

Adding Activities

Schedule Activity

  1. Open a GCGR.
  2. Click on the Labor Gantt tab.
  3. Hover over Add Activity at the top left.
  4. Select Schedule Activity.
  5. You will see required fields under Activity and optional fields under Sort Fields.
    1. ID is pre-filled automatically and in numerical order by last created ID.
    2. Label will be the name of the activity.
    3. Duration is set in quantity of days.
  6. Fill this out and select Save.
  7. You will see this Schedule Activity listed in the Labor Gantt as well as the Schedule module.

GR Labor Activity

  1. Open a GCGR.
  2. Click on the Labor Gantt tab.
  3. Hover over Add Activity at the top left.
  4. Select GR Labor Activity.
  5. You will see two required fields and a selection grid with Labor Types.
    1. Label will be the name of the GR Labor Category.
    2. Crew is a dropdown of existing crew options or you can create a new crew here.
  6. Fill this out and select your Labor Types for your crew.
  7. Click Save.
  8. You will see this GR Labor Activity listed in the GR Labor section of the Labor Gantt.

Linking Activities

In the Labor Gantt tab, you can link your Schedule activities to your Staff/Crew to better align when workers are scheduled. These are called relationships and can be edited through this view.

  • After creating a Schedule Activity, it will show up as a blue line in the Gantt view.
  • The Duration is important in showing how long this activity will be active on the project. The longer the duration, the longer your activity line will be in the Gantt view.

  • To link or create relationships between Activities and Staff/Crew, you can click into the Schedule Activity line, then with the arrows, you can align start and finish dates to the Staff/Crew that will be working on these activities.

  • If you edit the start and finish dates for staff in Labor Gantt by using the arrows or adjusting the duration, this will retroactively update the dates in the Staffing tab.
  • After you connect activities to the Staff/Crew, these will now be linked and a relationship has been formed.
  • To see the relationships you have created, simply click into any Activity line to see yellow arrows. These arrows are connected to the activities in which they are linked.

Labor Gantt Helpful Tips

  • Schedule Activities can be created in the Schedule module and the Labor Gantt tab within the GCs & GRs module. They will show in both views.
  • You have the ability to create new Crews via GR Labor Activities and have them show in both the Labor Gantt tab and the GRs Detail tab (these crews will not show in the GR Labor tab and vice versa).
  • After creating your Schedule and GR Labor Activities, you have the ability to edit those tasks.
    • Right-click the activity line and select Edit Activity.
    • You can also double-click the activity line.

  • GR Labor Categories (activity label) created through a GR Labor Activity will show in the GRs Detail tab under the Labor Items section.
    • The corresponding line item’s total will be the total value of the crew assigned to the activity (i.e. GR Labor Activity "A" with a 10 day duration has a crew of 1 laborer at a Regular Time rate of $60. This will equal 10 days * 8hr a day * 60).
  • Leads and Lags can be added between Schedule Activities and Staff/Crew via relationships by clicking on the yellow arrows.

  • Keep in mind, you will not be able to link certain activities together, such as Staff to GR Labor Activities or Staff to Staff. Ediphi only allows a Schedule Activity relationship to Staff/Crew.
  • Quantity Formulas are accessible in this view. These formulas are tied to estimates if you link the calculations. If the estimate is changed, it will adjust these Schedule Activities that have an active formula.

If you have any questions, feel free to contact our support team and we'll be happy to help!